Estimated TIME SCHEDULE (FOR B1 and B2 Connections)
Sr. #
Activity/Details
Days
PHASE 1
1
Registration
1
2
Survey & Estimation
5
3
Demand Notice (DN) of Capital Cost Security
7
PHASE TIME
13
PHASE 2 - After payment of DN and Test Report (where required)
1
Writing Test Report Verification
5
2
Service Connection Orders (SCO) / Material Release Order
5
3
Energization of Connection
10
PHASE TIME
17
TOTAL CONNECTION TIME
27
(Time taken by applicant for payment of DN excluded)
Procedural mechanism
1. The DN can be collected by the applicant on specific date given on the receipt of application from concerned office, otherwise it will be dispatched through post.
2. Payment of DN is to be made in the designated bank branch.
3. Test Report is to be submitted alongwith the payment of DN in the bank.
4. Test report shall be verified by concerned office. 5. Release Order will be issued by Sanctioning Authority along with SCO.